 |
| |
|
Sediment
and Stormwater Program |
| |
Program
Staff Program Overview Plan
Requirements Stormwater Facilities
Inspection Policies
Link to Green Tech Presentation |
|
| |
| |
| |
| |
| |
| |
|
Program Staff
- Jessica L. Watson,
Program Manager
- Edward Bender,
Stormwater Engineer
- John Bister, Stormwater
Engineer
- Jim Elliott ,
Sediment and Stormwater Plan Reviewer
- Charles Parsons , District Inspector
- Craig Mills ,
District Inspector
- Nathan Zimmerman ,
District Inspector
- Brent Shockley , District Inspector
- Cherie Stevenson, Maintenance Inspector
- Jennifer Grice,
Program Secretary
|
|
|
Program Overview |
| Delaware’s Department
of Natural Resources and Environmental Control is responsible for implementation
of the Sediment and Stormwater Management Program initiated July 1, 1991.
The responsibility to regulate this program was delegated to the Sussex
Conversation District for the entire county.
The District’s responsibilities under the Sediment and Stormwater
Regulations include the following:
- Review Sediment and Stormwater Management Plans for compliance with
Delaware’s Regulations.
- Approve Sediment and Stormwater Management Plans.
- Inspect the construction and compliance of approved Sediment and
Stormwater Management Plans.
- Annual inspection of permanent Stormwater Facilities.
- Assist and educate local communities on management of stormwater facilities.
|
|
Plan Requirements |
| A Sediment and Stormwater
Management Plan is required when land disturbing activity is 5,000
square feet or greater. The Sediment and Stormwater Management Plan
is to be submitted to the District for review and no site work is
to commence until the plan has been approved.
Land disturbing activity can be defined as “change or construction
activity for residential, commercial, silvicultural, industrial,
and institutional land use which may result in soil erosion from
water or wind or movement of sediments or pollutants into State
waters or onto lands in the State, or which may result in accelerated
stormwater runoff, including, but not limited to, clearing, grading,
excavating, transporting and filling of land.” (Section 2
#19) |
 |
|
| Those activities that are exempt
from submitting a Sediment and Stormwater Management Plan include the
following:
1. Activities for agricultural land management practices
2. Projects in which construction disturbs less than 5,000 square feet
3. Land activities that are regulated under specific State or Federal
laws
4. Projects which are emergency in nature and are necessary to protect
life or property. The appropriate plan approval agency shall determine
and approve of the emergency nature of the project.
To initiate the plan review process, the following items must be submitted
to the Sussex Conservation District:
- Completed application signed by the owner
- One set of plans and calculations
- Completed Checklist
- Review fee
If any of the above items have not been provided or an incomplete stormwater
management plan has been submitted, the District reserves the right to
return the plan without initiating the review process. The normal review
time for plans will be 30 days from the time a complete submittal package
is received by SCD. |
|
Stormwater Management Facilities |
| All submitted Sediment
and Stormwater Management Plans must adequately address how stormwater
quantity and quality treatment will be achieved.
Quantity Management:
Projects are to be designed to release the peak discharge for the 2 and
10-year frequency storms at a rate not to exceed the pre-development peak
discharge rates for the 2 and 10-year frequency storm events. Calculations
provided to the District are to include the 100-year storm elevation and
must demonstrate safe conveyance of that storm.
Quality Management:
Stormwater management practices must achieve an 80 percent reduction in
suspended solids load after a site has been developed. |
|
Inspection: |
| All approved projects are
required to schedule a pre-construction meeting with the Sussex Conservation
District prior to the commencement of any site disturbance. The District
Inspector will monitor the site developments on a weekly or biweekly basis
depending on the phase of construction. District inspection procedures
include the following:
- Pre-construction meeting prior to site disturbance.
- Implementation of erosion and sediment control practices as specified
on the approved Sediment and Stormwater Plan.
- District Inspector monitors compliance with the approved plan and generates
inspection reports to guide the contractor and developer through various
phases of construction.
- Inspect the construction of the stormwater management facility.
|
|
Policies: |
| Click on the links below for Printable
versions of the following forms: |
| As-Built
Checklist |
| Sediment
and Stormwater Management Checklist |
| Sediment and
Stormwater Review & Inspection Fees |
| Sediment
and Stormwater Certified Construction Reviewer Policy |
| |
|
|
| |